I have a fixed price contract that has a long list of tasks to be performed but is somewhat vague on the details. The contractor said a number of times "well we could do this" and the this was not on the list. No mention was made of additional payment for it.
My typical response was "are you sure about that - there's already a lot to do". In some cases I just said "yes that sounds good".
The contractor has become surly because the amount of time being spent is well greater than the amount he had anticipated. (Note: I have not "held" him to the contract - if he wants to leave he can).
He has now come forward saying he will put a lien on the house for items that are not in the original list. Will he win a judgment on this?
My problems with this:
- he came to me saying he would give me a bargain price.
- I was not even planning to do many parts of the work: he offered to do them at a low total price and I accepted
- I would not likely have agreed to the "extra" things if I had known there would be additional charges
- In any case I would most certainly not agree to the kinds of prices that he is now presenting: I could get lower prices from other tradespersons.
- Even given all that I would not likely have agreed to have the additional work done before the items on the original list were completed
If I were to have these additional work items done then I have been denied the opportunity to do a bidding/negotation/ terms / agreement cycle.
I never signed anything to pay a dime over the contract amount, or even verbally agreed to additional costs. Instead I frequently harped on my limited expenses ability and the fact that labor and materials were well over the estimates.
My take on this is his claim will not fly - there is no definitive evidence that I approved additional compensation for the additional items he did. At worst case the additional items would be costed out on a similar basis to the items in the original list. That amount of money I can handle- it is an order of magnitude less than the costs he is trying to impose now.
Having said all that - having a lien on the home is a real headache. My question would be along the lines of: would I be likely correct in the following
- most likely no judgement since lacking an indicator that I were expected to pay more
- if a judgment were allowed its magnitude should be aligned with the pricing of the original contract - not market rate
- having a lien filed will in any case be a long arduous headache of a process to deal with even though the claim would have limited or little merit
Update Apparently there is some chance a contractor might be able to get market rate for additional work even though the existing work was at a much lower rate. That is concerning. So here is more info.
There were numerous discussions that my finances were constrained, that he was providing a cut-rate service to help out, and that i needed to control any additional expenses. We came to a conclusion some time in that any new work would require a change order. He agreed in a text message and verbally that I had met any existing payments by virtue of retroactively reimbursing some fuel costs. He is now reneging on that as well as the spirit of the deal.
Epilogue
I made a settlement with this huckster. I would have likely won on merits against a lien - but the amount of the settlement was low enough to justify expediting the whole thing. It is a matter of having trusted too much and trusting the wrong person. There is a big cost associated with that class of mistakes.
Now the day after a very explicit "final" settlement - in which there is specific verbage that no further charges can be levied - this guy insists on adding a surcharge to materials that were already paid for or he won't deliver them. I just denied denied denied. "No more addition charges". The point here is: this is a guy just out to get as much as he can. Justice is NOT being served: just be careful to detect these folks before doing business with them!